# Under overhead (which does not need to be tracked) are listed:
# 	. technical consulting for Tech. support and Marketing
#	. TWG involvement based on reading notes, posting replies and 
#	  keeping track of proposals that affect us
#	. project documents maintenance
#	. building nightly/weekly development systems for group distributions
#	. group and program team meetings
#	. monthly project and objectives, weekly objectives
#	. coordinate with partners since it is mainly based on interrupts
#	. time spent doing schedule estimates

# NOTE: Tasks completed since the last update have been listed first.  Next
# revision they will be moved to the bottom.  The task left are listed in
# somewhat a priority order. Time spent is time since 1/19

NAME: Darren Smith

Time   Time    Orig.    Category	Task Description
spent  left    Est.

# Tasks completed through October 2, 1987.
# Overhead includes normal stuff.
2	0	0	Doc		RPC Programmer's Guide review
9	0.0	19.5	Test		Test and debug RPC/XDR (kernel code)
					o Misc. bug tracking/fixing.
					o Fixed only one nfsd problem (finally)
					o Fixed a few nfs bugs also.
0	0	5	Test		Final Code Reviews
					o Areas identified by BFA
2	0	6	Test		Code Review High risk code.
					o Sub-sec of port/test RPC/XDR
					o Code reviewed xdr_rec.c for JAD.
					o Code revieded some code as changes
					were made for bug fixes.
					o Some code review done driven by BFA

# Tasks to be worked on, priority order.

6	2	7	Test		70 % BFA coverage.
					o Created RPC test/debug tool.
					o Need to get to 70% and then automate
Checkpoint	BITREL	10/7/87

0	5	10	Test		85 % BFA coverage. (Goal)
					o At least need to get 70% automated.
0	2	2	Test		Final installation testing.
0	0.1	0	Sup		Release Celebration planned.
0	5	0	Doc		Post-mortem complete or planned.
0	1	0	Sup		All tools, etc. archived.
2	2	4	FTO		Vacation
Checkpoint	MR	12/02/87


# No time estimated for following tasks:
0	0	0	Dev		Provide optional kernel configurability
0	0	0	SSIT		SSIT activities
0	0	0	Test		Multi-vendor connectivity testing
0	0	0	Test		Reliability testing
0	0	0 	Test		Test opt. conf. capabilities of kernel 
0	0	0 	Test		Test operational interac. of NFS and DUX
0	0	0	Test		Release final bits to SSIT    
0	0	0	Train		Courses	

# COMPLETED TASKS
0.5	0	0.5	Doc		modify brick pages and provide examples
					o Completed for first pass at manuals.
2.0	0	0	Mkt		participation at Uniforum
					o 350->840 problem resolution(Completed)
1	0	2  	Test		Shared/Common scaffold work.
					o Completed?  Provided reviews/feedback
					 about proposal.  Will remain contact
					 for group, but remainder of time
					 should be small and interrupt driven.
0.25	0	1	Tool		Learning tools
					o Learned how to use BFA from Mikey
					 and read up on new cscope.  Don't
					 anticpate many other tools to learn.
0.5	0	10	Sup		Administrate test systems and equipment
    					(Two days a month for 5 months)
					o Completed (for me), since respons.
					 has been passed to JAD and GMF.
2	0	2       Test		Initial BFA numbers/setup for kernel
					o While Mikey did the initial invest.,
					 I worked on a script to automate the
					 process.  Still need to get initial
					 numbers from tests to drive testplan.

0.25	0	2	Iss	     	Follow-up efforts on long file names
					o passed to Mikey

4.5	0	5	Test		Test and debug RPC/XDR (kernel code)
					o Time broken out for testplan inputs
						for transformers.

0.25	0.0	1	Doc		provide technical info to documentation
					o Provide Annette info about SUN vs. HP
					  differeneces, anomalies, etc.
					o Taken care of largely by chm's ERS.

5.5	0	3	Tool		Dev. env. support/maintenance
					o May be misc. support tasks left
					but these are interrupt driven and
					covered by overhead.
# Completed tasks from 2/24 to 3/13
# NOTE: Overhead tasks worked on in this time frame include looking at commands
# that are not working with ISO and that are needed by Transformers (includes
# getting find and tar working so that we can mount the scaffold remotely.) Also
# created a script that tells up what has changed between one version of the
# kernel and the next (requested by Jim Hunter).  I have also been helping
# SSO some when they have had problems with connectivity. Finally, I have been
# working with Mikey and George on various kernel problems.
2	0	0	FTO		Vacation
					o Vacation time before Code Complete
# Tasks completed from 3/31 through 4/9
4	0	1	Doc		first documentation review
					o Note extra time because responsible
					for review of entire manual.

# Tasks completed through 4/28

5	0	3	Dev		IRS for RPC/NFS interactions 
					o I just made a bad original
					 estimate about the amount of time
					 it would take.

15	0	10	Dev		Port RPC/XDR (kernel code)
					o Fixed timeout/interrupt bug.
					o Helped Mikey with interrupt stuff.
					o Helped ISO track down ESTALE
					  problem.
					o Helped Dave track down RPC/XDR
					  user-level killer BUG while JAD was
					  on FTO.  Dave descibed as showstopper.
					o Helped Mikey with various problems.
					o Everything left should be bug fixes.


# NOTE: Overhead since last update includes 1) Proving security hole
# exists that allows a normal user on one system using only the socket
# interface to access files via NFS that do not belong to him, 2) Helping
# John and Marie figure out a problem with NFS/RPC that turns out to be yet
# another version of the "no transaction ID for non-idempotent requests" bug,
# and 3) normal other misc. overhead, like handling the hardware crash of DU.,
# tracking down the latest version of the ".." problem, etc.

0	0	4 	Test		add debug and trace code
					o Picked up from gmf.
					o NOTE: 5/6/87 Time set to zero since
					  looks unneccessary at present time

# Tasks completed through 6/05/87

# Overhead during last period includes trouble shooting various problems
# with EB1 and the LAB meetings, etc. that we had.
# Also spent time helping the Transformers with various problems, only
# some of which were related to NFS.  Also spent time on administering
# hpcndu/hpcndk to a certain extent, though not much.  Also made
# changes to the kernel build process for exchaning archives with the
# other groups and cleaned up the build process a little.

5	0	0	Sup		Help with self-host hpcndu/hpcndk
					o Includes time spent with actual
					  self-hosting, problems with the LAN
					  switch-over, and trouble shooting
					  problems noticed because of 
					  update to EB1, and working on
					  mail/lp.
0	0	3	Test		50 % BFA coverage.
					o No time spent because first pass
					at BFA reached 56%.
# Tasks completed through June 19, 1987:
# Major tasks worked on during previous period include Documentation reviews
# and Kernel Swat team on the Discless/NFS nsp panic.  Also spent time
# attending NFS/800 teleconferences to talk about code sharing, and working
# on NFS/RPC problems/bugs.
5	0	1	Doc		second documentation review
					o Extra time added because of over-
					all review responsibility and increased
					(better) coverage of PI.

# Tasks complete through June 29, 1987
# Overhead in this period includes yearly evaluation.  Also worked on
# discless panics, and the NFS kernel code sharing proposal.

# Tasks complete through July 15, 1987
# Tasks worked on in this time period include trouble-shooting the problem
# the LISP group was having (bad card) and a symbolic link problem Jason
# was seeing with Discless/NFS (SSO BUG), finalized code sharing agreement,
# began looking at code sharing implementation, plus working on various bugs.

10     0       0        New		Port RPC/XDR (+ kernel SWAT TEAM)
					o July 9, tracked down symbolic
					  link bug with NFS/Discless.
					o June 20-29, more Discless/NFS
					  problems, but found quicker.
					o June 9-19, worked on Discless/NFS
					  nsp panic problem.  (NASTY!!!!)
# Tasks worked on through August 3, 1987.
# Fixed several bugs in NFS/RPC.  Also looked at two panics in transformers
# systems (both RPC problems).  Manual review of RPC Programmer's Guide.
# Talked with Mikey sync problem.  Updated du/dk to EB2.  Helped mak update
# the rest of the test machines to EB2.  Consulted with Frederic on some
# of the problems he was having with testing.  Talked some with Carole about
# the configuration information.  Misc. other interruptions.
1	0	0	FTO		Vacation on July 20, 1987
2	0	0	New		RPC Programming Guide Reviews
					o Didn't plan for it in this time period
					o Took more time than discussed.

# Tasks completed thru Aug. 19, 1987
# Overhead in this time period includes:
# Lab meeting, New pay scale meeting, consultation with Ruth Lutes about
# NFS discless vs. our discless, helped Mark Kepke figure out kernel
# profiling, consult with Charlie Solomon about RPC standards, and of
# course, all the normal various interrupts and overhead.
0.5	0	1	Tech		SE class review/edit 7/24/87
0.5     0       0       Dev		Define/document revision number info.
25      0       0       Dev		Port RPC/XDR (+ kernel SWAT TEAM)
					o Fixed various bugs in DTS (two 
					  panics).  Tracked down corrupted
					  data problem.  Helped Mikey with
					  sync and logging.
					o Looked at LISP team's corrupted
					  data problem -- BAD CARD
					o Merged with NFS code from Stacy M.,
					  tracked down various problems
					  including going through a gateway.
					o Picked up from gmf.
					o Looked at various problems, 
					  including rpc.mountd problem and
					  the nfs_svc problem when given
					  a TCP socket instead of UDP.
					o Tracked down latest version of ".."
					  bug (/bin/sh problem..)
					o June 1-3.  Tracked down cr_get()
					  panic which was holding up Gobots
0.5     0       0       Tech            Document Configuration considerations
					  for NFS for Carole and Annette.
					o Location of commands issues.
2       0       0       Doc             Document/define NFS memory and
					 configurablility requirements
					o document # network connections


# Tasks completed through September 17, 1987
2	0	0	FTO		Vacation Aug. 20-21, 1987.
2	0	0	FTO		Sick Sept. 1-2.
1       0       0       Dev             Long File name recommendations
					o Talked to Annette
					o Carole, Andy know situation
1.25    0	0	Train		Monkey videos, Aug. 24-29.
9	0	0	New		Work out code sharing plans for kernel
					o Have Implemented checkin/out routines
					  using rmtrcs.  
					o NOTE: Problems with Internet!
					o Still need to write overnight scripts
					o Coordinate with jad, ISO, IND
					o Reached agreement on 7/1
					o Made rmtrcs work for us.
					o Need to implement planned mechanism
					o Interrupt driven now.
2	0	1	Doc		third documentation review
					o Extra time added because of over-
					all review responsibility and increased
					(better) coverage of PI.
0	0	2	A/B		support of Alpha/Beta and B.O. sites
					o DAE is handling this.
1	0	3	Coord		Track kernel modifications 
					o Bug fixes mostly from now on.
Checkpoint	EB3	8/17/87


# Have to be through by now:
Checkpoint 	END	12/31/87