              CND 9000/300 6.0 Networking Program Lifecycle
                 NFS and Networking Convergence for s300
                 
 
 
 


 
                              
                              
                              
                               Abstract
                               
  This document has two major objectives.  The first of these objectives
  is to provide logical program milestones or checkpoints.  These
  logical checkpoints are an outgrowth of each of the individual CND
  project team schedules which are involved in the series 300 6.0 release.
  The intent of these  checkpoints is to allow project and program 
  management to focus on goals which have significance for the majority
  of the program team.  The second objective of this document is to
  centralize a list of the major dependencies which the involved project
  teams have on each other or on external entities.  
  
  
  
  Authors:   Bill Mowson   2/87 - 3/87
	     Dan Simula    4/87 - 6/87
	     Jeff Lindberg 6/87 - 
  

  
  
  
                            Introduction
                            
 Colorado Networking Division has recently undertaken the aggressive
 goal of completing NFS functionality and networking architecture
 convergence on the 9000/300 in time for product shipments with 
 the system 6.0 release in September of 1987.  Subsequently, four
 project teams within Jim Willits' Technical Systems Networking 
 section have been mobilized to meet these objectives.  The project
 teams are organized as follows: 
   
 Project Name    Responsibility          Project Manager   #MTS     Start Date
 
 NERFS         NFS code port and fix      Jeff Lindberg     5         8/1/86
     
 TRANSFORMERS  NFS code testing           Dan Simula        3        12/19/86
 
 PEKING        Converged kernel port      Dean Thompson     6         8/1/86
 
 SMELTER       Converged NS/ARPA test     Chris Fugitt      5        12/19/86
     
 
 Other 6.0 program related activities at CND include:
 
 DOC           Technical Documentation    Annette Parsons (NFS)      10/1/86
                                          Mickie Calkins  (Convergence)
                                          
 TECH          Technical Support          Carole Crall               10/1/86
                                          
 PROD          Product Marketing          Andy Drol       (NFS)      10/1/86
                                          Laurie Miller   (Convergence)
 
 QA            Quality Assurance          Chuck Morse                 1/1/87
 

 With the number of project teams and MTS's involved in this program
 and its accelerated schedule, it is anticipated that smooth inter and
 intra project planning and scheduling will be difficult.  The intent
 of this document is to provide major program checkpoints to which all
 involved projects can manage accordingly.  This document was derived
 from the following documents:
 
    1) Document:  Project Lifecycle for Nerfs 300 program
       Author:    Mike Shipley
       Revision:  23 Jan 1987
       
    2) Document:  Project Lifecycle Specification - Project Peking
       Author:    Dean Thompson
       Revision:  22 Jan 1987
       
    3) Document:  Smelter Lifecycle for 300 Program
       Author:    Chris Fugitt
       Revision:  22 Jan 1987
     
    4) Document:  Project Transformers Lifecycle
       Author:    Bill Mowson
       Revision:  23 Jan 1987
       
    5) Document:  HP NFS Series 300 and Series 800 Documentation Plan
       Author:    Annette Parsons          
       Revision:  23 January 1987

    6) Document:  NFS Product Support Plan
       Author:    Carole Crall
       Revision:  31 January 1987

    7) Document:  Documentation Plan for 1.1 and 6.0 NFS and Convergence
		  Projects
       Author:    Mickie Calkins
       Revision:  09 June 1987

 

 Since this lifecycle is intended to be a reflection and coalescence
 of the individual project lifecycles, it is anticipated that a new
 revision of this document will be built after each checkpoint.
 These updates will consist of two important elements:
 
    1) A program synopsis of the major results, concerns, and issues 
       which occurred in the last phase of the program.  The last phase of
       the program is defined as the time between the last checkpoint
       and its immediate predecessor.  It is hoped that this synopsis
       will be helpful in:
           a) creating more effective plans to meet the next checkpoint
           b) the final post mortem analysis of the project
       
       Deliverables and dependencies which are not met on the specified
       date are denoted with a series of asterisks as follows:
       
          *** items which are of high importance to the program team
              and have not shown significant progress are denoted with
              three asterisks
              
           ** items which are of high importance to the program team
              and are near completion or partially usable are denoted
              with two asterisks
       
            * items which are of some importance to the program team or
              have had "negotiated" changes based on new data are
              denoted with one asterisk
              
           
    2) Updates to the deliverables and dependencies list of the next
       checkpoint for each project team.  These updates will be based
       on new data or recent necessary changes in the individual 
       project plans.  
   
                            
 Checkpoint dates shown in this document are currently targets or goals.
 These dates will solidify as "bottoms up" schedules become available
 from the individual project groups.  The goal for finalized checkpoint
 dates and schedule commitments is February 24th (I/L checkpoint).

                            
                            
                            
                            
                     Management of Dependencies
                     

 Key project and program dependencies are listed within this document.
 These dependencies are sorted first by applicable checkpoint, then by
 the owner (or holder) of the dependency, and lastly by the time at which
 they occur.  The following process is recommended for managing the project 
 dependencies specified within this document:

   1) The owner of the dependency is the manager (and team) that the
      dependency is on.  For example if the TRANSFORMERS project needs
      functional NFS code from the NERFS team by March 1st, then the
      NERFS manager (and team) should own and manage to this dependency 
      as a deliverable to the TRANSFORMERS team.
      
   2) The dependency list should be reviewed regularly at program team
      meetings.  Major upcoming dependencies should be brought up at
      program meetings as reminders to the responsible managers.
      
   3) Dependencies which are not met become a concern for the program
      and should be worked out as quickly as possible by the 
      responsible manager (the owner) and the requesting manager.
      All dependencies which are not met will be enumerated in this
      document as the program progresses. 

       

                     
                     
 Checkpoint:    Definition Complete
                   * NERFS checkpoint of Definition Complete
 
 Target Date:   Feb 10th, 1987
 
 Deliverables:
  
            NERFS
             * 1) ERS for NFS functionality (man pages)
                  - most man pages complete
                  - project ERS not complete
            ** 2) NFS performance benchmarks identified
                  - performance benchmarks not identified
             * 3) Preliminary NFS system Test plan
                  - responsibility moved to TRANS group
             * 4) Review of System Test, Product, and Documentation Plans
                  - system test plan not complete for review
               5) Equipment plans in place
               6) Man pages submitted as RFCs
             * 7) First project PERT
                  - PERT redefined to be a schedule
                            
            TRANSFORMERS
               8) Test porting investigation complete           
               9) NFS Quick Regression Test suite available
              10) System Test plan template complete  
            * 11) Start formal DTS on NFS
                  - code and test environment not stable enough to 
                    start formal DTS
              12) Quality metrics defined and system in place   

               

 Dependencies:                         On Whom      By Whom       By When
 
 1) Usable BFA for NFS kernel and user   SET         NERFS        2/10/87
  
 2) NFS System Test Plan template       TRANS        NERFS        2/6/87   **
     - had to wait until 2/15 for NERFS inputs to complete test plan
 
 3) RFA/NFS Examples and comparisons    NERFS        PROD         2/10/87 


        
 
                     
                     
 Checkpoint:    Design Complete / I to L
                    * NERFS checkpoint of Design Complete
                    * TRANS checkpoint of Planning Complete
                    * PEKING checkpoint of I/L
                    * SMELTER checkpoint of Start Formal Defect Tracking
                *** Checkpoint meeting ***
 
 Target Date:   Feb 24th, 1987
 
 Deliverables:
  
            NERFS
            ** 1) 80% NFS functionality including:
                     a) YP
                     b) Discless
                     c) PC-NFS daemon
                  - code at 88% functionality but YP and PC-NFS daemon
                    not yet functional 
             * 2) A self hostable NFS 300 system
                  - system not yet self hostable but not required in this
                    timeframe due to 6.0 system slip and lack of equipment
           *** 3) First official performance benchmark
                  - performance benchmarks not yet performed
             * 4) IRS complete and reviewed
                  - IRS's not needed for development of ported code
                  - will be completed by MR for support group's use
               5) All module test plans complete
               6) Man pages submitted to TWG and NSG
               7) System build process in place
               8) Installation procedure defined
               9) Project metrics identified and in place
                            
            TRANSFORMERS
              10) NFS System Test Plan complete and reviewed
              11) All project deliverables and dates defined
              12) NFS Program Lifecycle complete and reviewed
              13) Scaffold and NFS test environment defined
                  and implemented
            * 14) Final 50% and 90% confidence project schedules
                  - 90% project schedules not generated
           ** 15) Quick Regression 
                  - All tests complete except YP and mount because of lack
                    of functionality in existing code
                  - QR not being executed as part of build process
                    
            PEKING
              16) Updated PRD and PDS
              17) Finalized project objectives
              18) Final project schedule and manpower allocations
              19) All ES's updated    
              
            SMELTER
              20) Standard test scaffold and tools defined and
                  implemented
            * 21) Final A/B and NS service specifications
                  - minor issue outstanding with NLS in NFT
              22) Final Test Plans
              23) Defect Tracking system in place
            * 24) Quicky regression test operational for A/B and NS services
                  - functional problems with rlogin
                  - QR not being executed as part of build process
            * 25) Skeleton of element 4 in the standard regression suite
                  operational
                  - tests runnable but limited test progress made due to
                    system panics
              
            PROD
              26) Final Product Plan for NFS
              27) Early release and Beta test sites identified
              28) Final Product Plan for 6.0 networking
              29) Product Data Sheet complete
              30) Schedule complete
            * 31) Beta Test site plans complete
                  - Final Beta sites not yet selected 
            * 32) Price and Financial analysis complete
                  - NFS Pricing not yet solidified
              33) Merchandising Plan complete
 
            DOC
              34) Final Documentation Plan for NFS
              35) 2nd Draft Documentation Plan for 6.0 Networking
 
            TECH
              36) Preliminary Addendum of NS ARPA/300 Support plan
              37) Preliminary Product Support Plan
              38) Preliminary Training Plan
              39) Product Demo plan complete
              40) Beta Test Site plans complete 
               

 Dependencies:                         On Whom      By Whom       By When
 
 1) High priority system commands which  ISO         NERFS        2/24/87 **
    are affected by NFS are functional
    - don't have mount/unmount yet
                    
 2) Agreement on standard test          TRANS        SMELT        2/13/87 
    scaffold
 
 3) Quick Validation Process            TRANS        NERFS        2/24/87 
 
 4) Build and Distribution process      PEKING       NERFS        2/13/87  ***
    in place and functional                          SMELT
    - not running QR tests for NFS or AB/NS
    - no code sync with IND yet
 
 5) Shared code agreements finalized    PEKING       SMELT        2/13/87  ***
    with IND
    - agreements in place but have
      not completed code sync

 6) Services "quicky" tests running     PEKING       SMELT        2/18/87  ***
    as part of system release
    - QR not in place for release process
    
 7) Agreement on standard test          SMELT        TRANS        1/30/87  **
    scaffold
    - not yet negotiated with IND
    
 8) NS/ARPA Services Specification      SMELT         DOC         2/20/87

 9) Discless testing agreements          SSO         TRANS        2/6/87
 
 10) Installation procedures            NERFS         DOC         2/9/87
                                                      TECH

 11) Configuration procedures           NERFS         DOC         2/11/87
                                                      TECH
 
 12) NFS System Test Plan inputs        NERFS        TRANS        2/13/87
 
 13) Automatic System Distribution      NERFS        TRANS        2/13/87
 
 14) Maintenance Procedures             NERFS         DOC         2/18/87
                                                      TECH
 
 15) Network error messages             NERFS         DOC         2/20/87  *
                                                      TECH
     - moved to a future checkpoint
 
 16) NFS System Test Plan reviewed      NERFS        TRANS        2/21/87
 
 17) Defect Turnaround time goals       NERFS        TRANS        2/20/87  *
     - current "swat team" process is sufficient     

 18) HP and Sun NFS differences         NERFS         DOC         2/20/87 
                                                      TECH 

 19) New NFS and HP-UX reference        NERFS         DOC         2/23/87
     pages                                            TECH
 
 20) Project Lifecycles complete         ALL         TRANS        2/10/87 

 21) All partners using DTS              ALL         SMELT        2/18/87 

 22) 300 Product structure solidified    PROD         DOC         2/13/87

 23) Necessary modification for source   IND         PEKING       2/13/87
     code sharing

 24) Process for obtaining source        IND         PEKING       2/13/87  *
     from source control functional
     - defined but untried

                      
                      
 Checkpoint:    Stable System      
                    * TRANS 24 Hour NFS reliability
                    * PEKING first build for SSIT 
 
 Target Date:   March 16th, 1987
 
 Deliverables:

            NERFS
            ** 1) TWG and NSG approval for all affected man pages 
                  - NSG/TWG process still being defined
             * 2) ALPHA site release distribution 
                  - held off until EB1 code from SSO
 
            TRANSFORMERS
               3) 24 Hour 3 node NFS reliability with Level 1 stress
               4) Stress test suites complete
               5) 75% of NFS functional test suites complete
            ** 6) Initial connectivity test complete
                  - no PC testing yet due to late staffing
                  - no VMS testing due to lack of equipment
                  
            PEKING
               7) Source sync with IND completed
             * 8) Self hosted
                  - moved goal to April 1st to coincide with first SSIT
               9) Integrated LAN/NFS build functional
            * 10) All services and diagnostics functional
                  - rlogin problem understood but still unfixed (SSO fix)
            * 11) Bits Delivered to SSIT for first SSIT build
                  - SSO has slipped this to April 8th, but has not released
                    a final schedule
               

 Dependencies:                         On Whom      By Whom       By When
 
 1) Stable Level A system               NERFS        TRANS         3/2/87
 
 2) Self hostable NFS system            NERFS        TRANS         3/16/87  *
    - date changed
    - lack of usefulness due to 6.0 slip and lack of equipment
 
 3) Integrated Build                    NERFS        PEKING        3/15/87
 
 4) Code available for marketing        NERFS/        TECH         3/15/87
    systems and usability testing      PEKING

 5) System and command anomalies        NERFS/         DOC         3/15/87
    listed                             PEKING                          

 6) NS and ARPA services available      SMELT        PEKING        3/15/87
 
 7) First pass PC NFS testing complete   TIMO        TRANS         3/16/87  **
    - late staffing

 8) One additional 330 system            LAB         TRANS         2/23/87

 9) NFS Wollongong software avail.       LAB         TRANS         3/2/87   **
    - lack of funds
 
 10) One additional 350 system           LAB         TRANS         3/2/87   *
     - substituted a borrowed 310 and Kcat

 11) Two additional test systems         LAB         SMELT         2/18/87
     (330 and 350)

 12) Take over of hpcndm administration  SET          SMELT        2/18/87

 13) Additional kernel functionality     IND         PEKING        3/15/87   **
     - subnetting not expected until 4/15
     
 14) Final Product structure            PROD         PEKING        3/15/87   *
     - 300 and 800 structures may differ
     
 15) Preliminary on-line man pages        DOC         PEKING        3/15/87   *
     - not required until 4/1 for SSIT release

 16) Troubleshooting guides complete     TECH          DOC         3/6/87

 
 
                     
                     
 Checkpoint:    Code Complete / Enter QA
                     * NERFS code complete checkpoint
                     * PEKING functionality complete checkpoint
                     * SMELT 24 Hour reliability milestone
                *** Checkpoint meeting ***
 
 Target Date:   April 8th, 1987
 
 Deliverables:
 
            NERFS 
            ** 1) Full NFS functionality available
               2) 3.2 NFS defect fixes rolled in to kernel
               3) Performance goals met (75% of SUN)
            ** 4) All ERSs and IRSs updated
            ** 5) All QA metrics tools and processes in place

            PEKING
            ** 6) All kernel level functionalities present
               7) All administration and diagnostic functions present
            ** 8) Performance tuning complete (meets must objectives)
               9) Memory use tuning complete (meets must objectives)
            **10) Code reviews complete
                            
            SMELTER     
              11) A/B and NS services functionally complete
          *** 12) System passes 24 Hour three node mixed regression ring of 
                  300<->300,800 over single LAN and LAN/LAN gateway
            * 13) Berkeley sockets pass 12 Hour reliability tests to all
                  nodes which will be supported 
            * 14) System passes intersystem functional tests to all
                  supported HP nodes
              15) System passes 24 Hour homogeneous testing 300<->300,500,800
              16) System passes 24 Hour gateway connectivity (300 as gateway)
               
            DOC
              17) First draft NFS documentation available 

            TECH
              18) Usability testing complete


 Dependencies:                         On Whom      By Whom       By When
 
 1) Kernel performance and memory       PEKING       SMELT         4/8/87 **
    tuning complete  
 
 2) Networking kernel support,          PEKING       SMELT         4/8/87
    troubleshooting and timely
    defect repairs to pass std.
    regression test suite.
 
 3) Performance goals met               PEKING       NERFS         4/1/87

 4) Code portability issues             NERFS         DOC          3/18/87
    documented                                        TECH

 5) Inspection of first draft NFS       NERFS         DOC          3/30/87
    documentation complete              TECH
                                        DOC
                                        QA

 6) 50% of NFS affected commands         ISO         NERFS         4/2/87
 
 7) NFS corner case test suites         NERFS        TRANS         4/8/87 ***
 
 8) Scaffold for NFS                    TRANS        NERFS         4/2/87  

 9) Memory tuning complete,              IND         PEKING        4/1/87 **
    integrated and under source control 

 10) Performance tuning complete,        IND         PEKING        4/1/87 
    integrated and under source control 

 11) New kernel functions complete,      IND         PEKING        4/1/87  **
    integrated and under source control
    including:
           a) subnetting
           b) driver trace
           c) common event logging

 12) Stable kernel                       SSO         PEKING        4/1/87

 13) Stable and complete Vnode kernel    SSO         NERFS         4/1/87

 14) Performance goals met              PEKING       NERFS         4/1/87

 15) Pty and sendmail location issues     TWG         SMELT        3/25/87 **
     resolved 

 17) One additional s330                 LAB          TRANS         3/15/87 ***

 18) One additional development system   LAB          SMELT         3/25/87 **
     (350)
     
 19) SUN gateway configuration           LAB          TRANS         4/1/87

 20) Installation and Configuration      TECH          DOC          3/30/87
     usability testing complete          QA




Project Checkpoint

EARLY BIRD ONE RELEASE (EB1) 
	* NERFS first release to SSIT
	* PEKING first release to SSIT
	* TRANS 48 Hour NFS reliability
	* TECH release to EB1 test sites

Target Date:   May 12th, 1987

Deliverables: 							Completed:
    NERFS
	1)  IRS written and distributed				  5/01/87
	2)  Remaining QA metrics tools and processes in place	  5/01/87
	3)  Code development complete (NLS, error logging)	  8/17/87
	4)  Release procedure for final SSIT established	  5/01/87
	5)  Deliver NFS bits to SSIT for EB1	  		  5/01/87
	7)  Limited alpha site distribution	  		  5/01/87
	8)  Self hosted on hpcndu/hpcndk	  		  5/01/87

    TRANSFORMERS
	9)  48 Hour NFS system reliability at Level 2 stress	  4/18/87
	10) 95% of NFS functional test programs complete	  4/28/87
	11) Security test suites complete	  		  4/30/87
	12) System recovery test suites complete	  	  3/22/87
	13) Error condition test suites complete	  	  4/30/87
	14) Un*x/Un*x connectivity test suites complete	  	  4/22/87

    PEKING
	15) Deliver networking bits to SSIT for EB1		  5/01/87

    DOC 
	16) First draft of NFS documentation reviewed		  4/04/87
	17) Revised Convergence/NFS documentation plan		  4/30/87
	18) Convergence/NFS QA plan complete		  	  4/30/87
	19) On-line Convergence man pages provided		  3/15/87
	20) On-line README file complete			  3/15/87

    TECH 
	21) Early Release Support Plan updated and distributed	  4/28/87
	22) Verification Tool defined		  		  5/22/87
	23) Draft of troubleshooting for PEKING complete	  4/23/87
	24) Training Planning Package submitted to ASD		  4/27/87
	25) Data sheet submitted to ASD		  		  4/27/87

    PROD
	26) Beta Test Site agreements signed		  	  -------
	27) Notify MARCOM		  			  -------

 

Dependencies:				 On	    By		  Date:
					Whom:      Whom:        (est/comp)
 
1)  Stable Level B quality system       NERFS       TRANS         4/08/87
								  4/08/87

2)  Solid compilers                     SSO         PEKING        4/15/87
								  4/08/87

3)  Stable and complete V-node kernel   SSO         NERFS         4/24/87
								  4/08/87

4)  Final HP-UX pages available         NERFS       DOC           4/30/87
								  4/30/87

5)  Verification tool defined           NERFS       TECH          4/30/87
                                        TRANS 			  4/30/87

6)  Gateway connectivity available      TRANS       DOC           4/30/87 
								  4/30/87
   
7)  Latest on-line man pages for         DOC         PEKING        4/30/87
    CONVERGENCE only 						  4/30/87

8)  List of Beta test sites             PROD        TECH          4/30/87
								  4/30/87

9)  NFS/Discless interactions info      TECH        DOC           4/30/87
								  4/30/87
   
11) PC test suites complete             TIMO        TRANS         4/30/87
								  4/30/87

12) 100% of NFS affected commands       ISO         NERFS         5/06/87
								  6/1/87




Project Checkpoint

EARLY BIRD TWO RELEASE (EB2)                     
	* PEKING code freeze checkpoint
	* SMELT 24-hour reliability milestone
 
Target Date:   June 15th, 1987
 
Deliverables: 							Completed:
    NERFS
	1)  Discless and NFS inter-operability 			  6/15/87
	2)  Deliver NFS bits to SSIT for EB2		  	  6/22/87

    TRANS
	3)  100% of RPC/XDR/YP functional tests completed	  6/12/87
                      
    PEKING 
	4)  Plan in place for code change reviews                 5/28/87
	5)  Final code with defect fix exceptions		  6/11/87
	6)  Self host on development system (hpcndhf)		  5/12/87
	8)  Deliver networking kernel bits to SSIT for EB2	  6/24/87

    SMELTER
	9)  NS/ARPA services functionally complete		  6/15/87
	10) All 24-hour reliability testing complete		  see note
	    note:  all 300 related 24-hour stress-reliability
	    test configurations passed.  However, still have
	    outstanding panic in cluster testing.
	11) NS inter-system functional testing complete		  6/15/87
	12) Deliver NS/AB bits to SSIT for EB2		  	  6/24/87

    TECH
	13) Early code release training complete	  	  6/3/87
	14) BETA site support process in place		  	  5/29/87
	15) Final troubleshooting guide written and approved 	  6/16/87
	    by the NFS development team

    DOC
	17) Using and Administering NFS; 2nd draft available	  5/29/87
	    (Users' Guide / Admin Guide only)
	18) Programming with NFS; 1st draft available 		  5/29/87
	19) EB2 draft copies to partners			  7/09/87


Dependencies:				 On	    By		  Date:
					Whom:      Whom:        (est/comp)

3)  Networking kernel support,          PEKING      SMELT         as req. 
    troubleshooting and timely					  okay
    defect repairs to pass std.
    regression test suite.
 
4)  Stable system for training		TECH        LAB           5/15/87
								  5/28/87

5)  Questionnaire and support plans     TECH        NERFS         5/15/87
    for Beta test sites                 DOC			  5/15/87
                                        PROD
                                                  
6)  Documentation questionnaire for     DOC         TECH          5/15/87
    BETA test sites				  		  5/15/87
 
7)  On-line versions of man pages  	DOC         PEKING        5/22/87
    and README files available					  6/22/87

8)  PC NFS testing completed for EB2    TIMO        TRANS         5/24/87
								  5/24/87

9)  48 Hour reliability for NFS         TRANS       SMELT         5/27/87 
    and tests in scaffold					   DONE

10) Stable kernel                       SSO         PEKING        5/29/87
								   DONE

11) Agreement with IND for source       IND         PEKING        5/29/87
    code freeze					  		  5/28/87

13) Product installation tested         NERFS       DOC           5/29/87
								  5/12/87

14) Using and Administering NFS;	NERFS	    DOC		  5/29/87
    Second draft available			    TECH	  5/29/87
    
15) Programming with NFS;		NERFS	    DOC		  5/29/87
    First draft available			    TECH	  5/29/87

16) RND bridge available                LAB         TRANS         5/29/87
								  5/26/87

17) Stable Level C system		NERFS	    TRANS         6/01/87
					PEKING			  6/25/87

18) 1st draft of changes to ARPA        PEKING      DOC        	  6/09/87
    tutorials available      				 	  6/07/87

20) Second draft manuals for training   TECH        DOC           6/15/87
    (NFS only) (except programming)				  5/29/87
								  

 
 
Project Checkpoint

QA STATUS UPDATE   
 
Target Date:   June 22nd, 1987

Deliverables: 							Completed:

    NERFS
	4)  50% BFA coverage			  		  7/17/87
	5)  Man pages approved by NSG and TWG		  	  8/12/87

    TRANSFORMERS
	6)  100% of tests written (per System Test Plan)	  6/22/87
	7)  120 hour reliability at stress level II	  	  6/29/87
	8)  Sun gateway testing complete			  6/30/87
	9)  NFS/Discless interactions testing complete	  	  6/30/87
 
    DOC
	10) Using and Administering NFS (2nd draft)	  	  6/8/87
	12) NFS reference page edits complete			  6/18/87
 

Dependencies:				 On	    By		  Date:
					Whom:      Whom:        (est/comp)

1)  Self hosted with EB2 bits           PEKING      PEKING        6/15/87
								  6/24/87

2)  Final NS and A/B services           SMELT       PEKING        6/15/87
    (with exception of defect fixes)				  6/1/87
 
3)  Final man pages available           DOC         PEKING        6/15/87
								  6/22/87
 
4)  NFS interface definition frozen     ALL         DOC           6/15/87
								  8/17/87

5)  Begin Sales Training Manual         PROD        PROD          6/15/87
    and Technical literature  					   DONE

6)  Second Drafts of Using and          NERFS       DOC           6/16/87
    Administering NFS reviewed					  6/16/87

7)  Edited NFS reference pages          DOC         NERFS         6/18/87
								  6/22/87

8)  30% access to VMS/NFS system        LAB         TRANS         6/22/87
								  7/08/87


 
 
Program Checkpoint

BETA SITE RELEASE (EB2 distribution)
		* TRANS 120 Hour reliability milestone
		* SMELT 48 Hour reliability milestone
 
Target Date:   July 22nd, 1987
 
Deliverables: 							Completed:

    NERFS
	1)  Performance goals reconfirmed (using EB2)		  8/07/87
	2)  ALL STP test cases/suites complete by 7/22		  8/10/87
	3)  Distribute to alpha sites 				  8/06/87
 
    TRANS
	5)  120 hour NFS system reliability at level II stress	  6/29/87
	6)  100% of all test suites complete			  7/14/87
	7)  Security testing complete			  	  7/10/87
	8)  Recovery testing complete			  	  7/10/87
	9)  Error Condition testing complete			  7/13/87
	10) RND Bridge configuration testing complete		  7/06/87
	11) Un*x/Un*x connectivity testing complete		  7/14/87
	12) VMS test suites complete			  	  7/09/87

    SMELTER
	13) A/B and NS services code frozen 			  8/31/87
	15) ARPA services pass 24 Hour 	  			  okay
	    reliability tests to all supported nodes 
	    (selective testing, not shotgun approach)
	17) System passes 48 Hour gateway connectivity 	  	  7/14/87
	    (300 as gateway)
	18) 48 hour LAN-LAN mixed ring 				  8/28/87

    TECH
	22) Final TPP submitted/approved			  6/30/87

    DOC
	25) Programming with NFS; 2nd draft available		   DONE
	    (not in EB2 distribution)
	26) Existing ARPA manuals to partners, including	  7/09/87
	    1st draft of ARPA tutorials, Revised NS + ARPA
	    references, hard copy of installation read-me



Dependencies:				 On	    By		  Date:
					Whom:      Whom:        (est/comp)

2)  Freeze on product features          ALL          SMELT        7/05/87
								  8/17/87

3)  Second draft of all NFS manuals	NERFS	     DOC	  7/15/87
    complete				PEKING			  okay

4)  Convergence ref. pages reviewed     PEKING	     DOC	  7/22/87
								   DONE

5)  Configuration recommendations for   NERFS        TECH         8/01/87
    connecting to non-HP systems				  8/12/87

6)  1st draft of changes to ARPA        PEKING      DOC        	  7/20/87
    overview available      				 	   DONE

8)  NFS/Diskless interaction info	NERFS	     DOC	  7/24/87
								  8/20/87

9)  Examples for updating multiple	NERFS	     DOC	  7/17/87
    maps, modifying YP maps					  7/15/87

10)  NFS Virtual Home Environment	NERFS	     DOC	  7/15/87
     source documentation					  7/16/87

11)  NFS network memory limits		NERFS	     DOC	  7/24/87
								  8/12/87

12)  NS-ARPA network memory limits	PEKING	     DOC	  7/15/87
								   DONE

14)  Max number of NFS net connections	NERFS	     DOC	  7/24/87
								  8/12/87

15)  Source info for YP non-standard	NERFS	     DOC	  7/17/87
     maps section and changes to YP				  7/17/87
     master maps section

16)  NFS troubleshooting		TECH	     DOC	  7/17/87
								  7/20/87



Program Checkpoint

BASE SYSTEM RELEASE (EB3 will be the Base System)
		* Product Code Freeze
		* PEKING Complete QA

Target Date:   August 24, 1987

Deliverables: 							Completed:
    NERFS
	1)  Deliver NFS bits to SSIT for EB3/BASE system	  8/27/87
	2)  BFA code coverage: 60% user code; 70% kernel code      DONE
	3)  Code reviews complete for high risk code		   DONE

    TRANS
	4)  Pre-release regression testing completed		  8/24/87

    SMELTER
	5) System passes 120 Hour three node mixed regression 	   DONE
	    ring of 300<->300,800 over single LAN and LAN/LAN 
	    gateway
    PEKING
	5)  Deliver networking bits to SSIT for base system 	   DONE
	    build (EB3)
	6)  All kernel functional tests completed and executed	   DONE

    TECH
	7)  Presales course draft complete			  8/17/87
	8)  Performance testing complete                          8/9/87

    DOC
	10) Node Manager's guide 1st draft			   DONE
	11) Overview - final draft				   DONE
	12) NFS Using/Admin - final draft			   DONE
	13) Ref man pages - final draft				   DONE
	14) Programming w/NFS - 2nd draft			   DONE
	15) ARPA User's Guide - 1st draft			   DONE
	16) ARPA Tutorials - 1st draft				   DONE


Dependencies:				 On	    By		  Date:
					Whom:      Whom:        (est/comp)

1)  NFS functional test suites 		TRANS	    SMELT	  8/31/87
    integrated in Smelter test environ.				  9/7/87

2)  Provide EB2 release to AT&T		SSIT        TECH          8/1/87
								   DONE

3)  PC NFS testing (90%) completed      TIMO         TRANS        8/14/87
								  8/27/87

4)  120 Hour reliability in NFS         TRANS        SMELT        8/17/87
								   DONE

5)  Documentation from lab on		PEKING	     TECH 	  8/01/87
    multi-homing 				     DOC	  8/01/87

6)  Verification tool complete          LAB          TECH         11/30/87
    Assistance with using Sun test suite			  -------

7)  All 300/800 NFS differences		NERFS	     TECH	  10/15/87
    identified							   DONE

8)  Review NFS training complete	NERFS	     TECH	  8/14/87
								  8/5/87

9)  Review NFS training complete	PEKING	     TECH	  8/14/87
								  8/5/87

10) Feedback from BETA sites		TECH	     DOC	  8/17/87
    (only have one formal beta site)				   DONE

11) Move tags to head for all 		SSO CMDS     NERFS	  8/17/87
    header files and libc library files				   DONE



Program Checkpoint

FINAL SSIT RELEASE / QA COMPLETE 
		* NERFS  QA complete checkpoint
		* PEKING Final release to SSIT checkpoint 
		* PROD Release to Introduction

	*** Checkpoint meeting ***
 
Target Date:   October 7, 1987
 
Deliverables: 							Completed:
  
    NERFS
	1)  Final integration with SSO code			   DONE
	2)  Reconfirm performance goals			  	   DONE
	3)  No major defects in 120 Hour testing		   DONE
	4)  BFA code coverage (60% user; 70% kernel)  		   10/87
	5)  Deliver final NFS bits to SSIT			  10/23/87
	6)  Meet MUST-level FURPS objectives			   DONE
	7)  Code reviews complete (determined by BFA)		  DROPPED
	8)  Update NLS message catalogs				   DONE
    
    TRANSFORMERS
	8)  120 Hour system reliability at combined 		  10/20/87
	    networking stress
	9)  120 Hour NFS system reliability, level 3 stress	  10/20/87
	10) All connectivity testing complete			  10/16/87
	11) All system corner case testing complete		  10/16/87
	12) All NFS/Discless X-services testing complete	  10/23/87
	13) Info available for Quality statement 		  10/23/87

    PEKING
	14) All serious defects fixed			  	  ALMOST*
		*Still have 4 outstanding at release
	15) All defect resolved			  		   DONE
	16) All functional tests pass			  	   DONE
	17) All ARPA certification complete			   DONE
	18) All NS certification complete			   DONE
	19) 120 Hour reliability on all target topologies	   DONE
	20) Path coverage goals on new code met			   DONE
	21) Bits delivered to SSIT for final SSIT build		  10/21/87
 
    SMELTER
	22) System passes all tests for minimum acceptance 	   DONE
	    level; selective spot testing to reconfirm
		*Except for scaled back sockets tests, and
		 postponed Apollo connectivity tests

    TECH
	4)  Modifications to SE ARPA course complete	  	  -------
	5)  Draft of CE/SE NFS course complete			  9/14/87
	6)  Verification tools complete	  			  -------
	7)  Final PSP's submitted                        	  10/19/87
	9)  Final version NFS CE/SE course including 800 	  -------
	24) BETA test NFS customer course			  DROPPED
	25) Final Beta feedback (10/31)	  			   DONE

    PROD
	26) Final reports from test sites			   DONE
	(only have one formal beta site)
	
    DOC
	31) All NFS manuals released to printer 		  11/13/87
	32) All NS-ARPA manuals to printer        		  11/19/87

    QA
	33) Statement of quality supporting completion of QA	  
 

Dependencies:				 On	    By		  Date:
					Whom:      Whom:        (est/comp)

1)  Frozen kernel code available        SSO          NERFS        10/19/87
                                               			   DONE

2)  Installation testing of final       NERFS        TECH         11/30/87
    bits                                PEKING			  11/23

3)  Final LAN code available            PEKING       NERFS        10/3/87
								   DONE

4)  Final NFS commands code available   ISO/SSO      NERFS        10/3/87
								   DONE

5)  Final 120 Hour network testing      SMELT        TRANS        10/7/87 
								  10/7/87
 
6)  Final testing of NS and ARPA        SMELT        PEKING       10/7/87
    services  							   DONE

7)  Move tags to head for all 		SSO CMDS     NERFS	  10/7/87
    header files and libc library files				   DONE



Program Checkpoint

INTRODUCTION RELEASE
		* PROD Release to Introduction

	*** Checkpoint meeting ***
 
Target Date:   October 27th, 1987
 
Deliverables: 							Completed:
  
    NERFS
	1)  Re-deliver final NFS bits to SSIT if needed		   DONE
    
    PEKING
	2)  Re-deliver final Convergence bits to SSIT if needed	   DONE
 
    PROD
	DUE 11/20:
	3) Product pricing approved			  	   11/87
	4) Product introduction scheduled			   11/87
	5) Submit articles to IS&M News and DS&MA News		   11/87
	

Dependencies:				 On	    By		  Date:
					Whom:      Whom:        (est/comp)

1)  Final kernel code available         SSO          NERFS        10/19/87
                                               			   DONE




Program Checkpoint

MANUFACTURING RELEASE   
		*** Checkpoint meeting ***

Target Date:  December 17th, 1987
 
Deliverables: 							Completed:

NOTE:  Need to combine reports for Peking/Smelter and Nerfs/Transformers.
       (e.g. corporate metrics, quality reports, archive, etc.)

    NERFS
	1)  All defects resolved			  	  11/15
	2)  Installability testing complete			  11/24
	3)  Release celebration planned			  	  [12/31]
	4)  Corporate metrics complete (include TRANSFORMERS)	  12/4
	5)  Project post mortem complete or planned		  12/4
	6)  All code, documentation and tools archived		  12/4
	6)  Project history notebook				  [12/16]
	7)  Internal documentation complete			  [12/15]
	8)  NLS message catalog "translation guides"		  11/30
	9)  Check that tags are at head for all header files and 
	    libc library files before final SSIT complete  	  11/23

    TRANSFORMERS
	8)  NFS retest of final SSIT bits complete 		  11/23
	10) Project post mortem complete 		  	  11/30
	11) All NFS tests archived		  		  11/30

    PEKING
	12) Final product tape installed and verified 		  12/9
	13) All NS-ARPA code and tests archived 		  12/7
	14) Final quality report (with SMELTER)   		  -------
	15) Project post mortem complete		  	  -------
	16) Corporate metrics submitted (with SMELTER)		  12/9

    SMELT
	17) Retest of final networking bits 		  	  11/23

    DOC
	21) Documentation in stock by 12/11 	  		  [12/15]

    TECH
	22) Release NFS customer course to SDC (12/4)		  N/A
	23) NS/ARPA customer course modified  		  	  N/A
	24) Submit field articles        			  11/2/87
	25) Installability test checkoff		  	  11/24
	26) Serviceability test checkoff 		  	  11/24
	27) NCCS set-up                  		  	  -------

    PROD
	28) CPL becomes effective (12/1)	  		  12/1
	29) Final payment to SUN for perpetual license 		  [1/15/88]
 
    QA
	30) Quality summary, and statement of support for         12/11
	    release of product

Dependencies:				 On	    By		  Date:
					Whom:      Whom:        (est/comp)

1)  All ordering, pricing, bundling	PROD	     TECH	  11/1/87
    info solidified for inclusion in				   DONE
    final support plan.

4)  SE distribution of Manuals          SDC          TECH        12/23/87
								 --------

5)  SE distribution complete            MANF/SDC     TECH        12/23/87
								 --------



APPENDIX A:  Checkpoint Summaries

	
    Contents:

	       Checkpoint				  Date
	       ----------				  ----

	[1] Code Complete Checkpoint			4/30/87

	[2] Early Bird One Checkpoint (EB1)		5/12/87

	[3] Early Bird Two Checkpoint (EB2)		6/15/87




PROGRAM CHECKPOINT SUMMARY

Checkpoints: 
	    Code Complete
	    April 8th, 1987

	    BETA test release
	    April 30th, 1987


Program Synopsis:

	The primary objective associated with the April 8th code complete 
	checkpoint was functionally complete NFS and converged networking
	code.  A number of the checkpoint deliverables were not delivered 
	as originally planned (see below).  

	The BETA test release checkpoint (4/30) was effectively replaced 
	by the EB1 and EB2 system release checkpoints.  This replacement
	was caused by a revised HP-UX 6.0 schedule which forced a 2-1/4
	calendar month slip.  Numerous deliverables and dependencies 
	were redefined to account for the expanded project PERT.  In
	addition, project teams were de-staffed to a level commensurate
	with the remaining effort.


Issues/Concerns:

	[1]  A firm HP-UX 6.0 schedule is required from SSO in order
	     to solidify the deliverable and dependency dates in this
	     life cycle.  Until a firm schedule is obtained, it is likely
	     that this document will undergo frequent, and fairly major,
	     changes.

Deviations: 					Original  Revised  Completion
				 		  Date    Estimate   Date
    NERFS

        - full NFS functionality available	4/08/87	  5/01/87   DONE
	    o 5 engineering days left

        - All ERSs and IRSs updated		4/08/87   5/01/87   5/01/87
	    o 3 engineering days left

        - All QA metrics/processes in place	4/08/87   5/01/87   5/01/87

        - Code reviews complete			4/30/87	  6/22/87   DONE


    PEKING

        - All kernel functionality present	4/08/87   5/01/87   5/01/87

        - Performance tuning complete		4/08/87   6/01/87   -------
	    o did not meet RFA MUST objective
	    o re-evaluating

        - Code reviews complete			4/08/87   5/01/87   5/01/87


    SMELTER

        - 24 hour three node regression 	4/08/87   5/15/87   6/15/87
	  testing; single LAN and LAN-LAN


PROGRAM CHECKPOINT SUMMARY

Checkpoint: 
	    EARLY BIRD ONE RELEASE (EB1)
	    May 12th, 1987

Program Synopsis:

	The EB1 release represented the first formal release of partner
	subsystems to the HP-UX 6.0 SSIT process.  The HP-UX 6.0 EB1
	systems were released from SSIT on May 26th.  The EB1 system
	was given to a number of alpha-sites and to selected beta-sites 
	and business opportunities.

	As originally suspected, the EB1 release cycle revealed a number 
	of process problems.  These problems were related to subsystem
	builds, testing and delivery to SSIT.



Issues/Concerns:

	[1] The libc.a library was originally built without YP support.
	    This caused a turn of the EB1 bits after partner submittals
	    were complete.  Furthermore, rlogin and telnet services were
	    not rebuilt with the new libc and were released without the
	    necessary YP support.



Deviations: 					Original  Revised  Completion
				 		  Date    Estimate   Date
    NERFS

	- NLS Code development complete		5/12/87   -------   8/17/87


    PRODUCT MARKETING

	- Beta Test Site agreements signed	5/12/87   -------   -------
	- Notify MARCOM		  		5/12/87   -------   -------

